Performance reports are published for various aspects of the Planning service.
All in
format.
| Planning Service Peer Review Report published by the Planning Advisory Service April 2007 (1.43Mb) |
| Best Value Review of Development Control published by the Audit Commission November 2001. |
| The Annual Monitoring Report (AMR) assesses the Councils'
progress in producing the Local Development Documents and in
implementing policies.
Local Development
Framework Annual Monitoring Report December 2007
(720Kb).
|
| Enforcement Annual Report 2003 (140kb) |
From 1 April 2006 to 30 June 2007
From 1 April 2006 to 30 June 2006
From 1 November 2005 to 31 March 2006
Government expects all local planning authorities to perform at or above Best Value targets for development control by 2006.
The targets relate to the speed of determining planning applications and there are three classifications as follows:
| Application classification: | Target: |
| Major | 60% determined in 13 weeks |
| Minor | 65% determined in 8 weeks |
| Other (including householder) | 80% determined in 8 weeks |
The following three charts indicate the Council's current performance for each of these classes of application.
Speed of Determination of Planning Applications Rolling Annual BV109 Performance (41kb)
Planning Data Sheet (53kb)
Performance Indicators for Planning 2006/2007 (65kb)
Productivity is also an important aspect of development control performance for which there is no national standard. The following chart shows the number of planning applications received and determined by the Council in each financial year from 1997 to 2007.