DATE: 12 SEPTEMBER 2006 - PROGRESS
on the £8m Royal Hall restoration project is going well and
Harrogate Borough Council has revealed that more restoration work
can be carried out than had been originally anticipated.
Head of Property Management for Harrogate Borough Council,
Martin Weeks has vast experience of major
construction projects, but he says that planning this
restoration has been one of the most difficult he has worked
on: yet the project is now going well and this
is down to having a high quality design team and contractor, the
right contract strategy and all the investigative work which was
undertaken. There is a real partnership between
the council, its project team and the contractor HBG, all working
together for a successful outcome.
"This is an old beautiful building with a lot of things
waiting in the wings to go wrong", said Martin.
"However, the council was insistent that whatever work we could
achieve on this restoration could never go beyond the £8m
that had been put into the pot by the Heritage Lottery Fund and the
council. So we had to do a lot of work before we
ever got to the stage where we could let this 61 week
contract."
Risk assessments had identified that most of the unknown
problems should have come to light during the first four to five
months of the contract.
"The highest risk period has now nearly passed", added
Martin. "The extensive investigation of the
structure earlier on has paid dividends. We
don't expect to find any major hidden defects now and the
contingency sums we set aside at the start of the contract are
being used at a lower rate than we had
anticipated. This is good news because it means
that within the capped budget of £8 million we should be able
to achieve a bigger restoration than we originally thought."
After four months of work on site, progress on
the restoration contract continues to be good and council leader,
Councillor Mike Gardner, is pleased with the way the contract is
sticking to its timetable and that financially things are
progressing well.
He said: "We agreed to a carefully managed
project which meant that some large sections of the work were
deferred until we had confidence that we could afford to add them
back in. A large proportion of the works that
were being held back in this way, to make sure we stayed within
budget, are now being released as the project team is gaining in
certainty that there are no large hidden
problems. With the Restoration Trust's majestic
efforts on fund-raising, which to-date stand a little under
£900,000, we are also looking at a broader scope of
work. However, as we are doing more than we
originally planned, we may not finish the contract at the original
anticipated time. But for once, delayed
completion means good news. The Royal Hall will
probably re-open in late 2007." ENDS
PHOTOGRAPHS SUBMITTED:
0013 Basement - Construction work is underway to waterproof
and stabilise the structure. This will be the location of the new
ladies toilets.
0046 Scaffolding in the main auditorium to provide access for
paint scrapings to be taken from the original
ceiling. This is needed to establish the
original decoration colours to ensure authentic
redecoration. Floor protection and dust
screens together with dust extraction systems are in place.
0027 Ambulatory following demolition of this structurally
unsafe area, work is underway to provide new dressing rooms at the
lower level and restore the conservatory and ambulatory at the
higher level. The ambulatory is the corridor
encircling the building and this was originally used for
'promenading'. Reconstruction of this facility
is a key feature for restoring the architectural integrity of the
building.
NOTE TO EDITORS:
In addition to the £8million allocated to the core
scheme, (£2million from Harrogate Borough Council and
£6million from the Heritage Lottery Fund) the Royal Hall
Restoration Trust is also raising funds to make the Royal Hall an
attractive and inspiring performance venue once
again. To achieve this, the Trust's target is to
raise an additional £1.8 million to reinstate a number of
important works that are currently omitted from the core programme
on funding grounds.
HLF's substantial grant, along with Harrogate Borough
Council's contribution, will allow the rescue of this building,
which has been unused for some time.
The Royal Hall in Harrogate is one of the district's favourite
landmarks. This Frank Matcham building is
England's last surviving Kursaal and is steeped in history as well
as being an important community resource.