The Harrogate District Community Infrastructure Levy Charging Schedule was approved at Full Council on 8 July 2020 and will be implemented from 1 October 2020. Any new applications submitted after the approval date of 8 July 2020 and determined on or after the 1 October 2020 will be liable for CIL (if meeting the criteria under the charging schedule).

The introduction of the levy means that additional information is required on submission of a planning application to determine whether a charge is due and to determine the amount.

Applicants are therefore required to submit a CIL Form 1: Additional information along with the planning application which can be done through the Planning Portal.


Community Infrastructure Levy Examination

This page forms the main source of information regarding the CIL Examination. The information should be read alongside the submission and supporting documents.

Inspector

Jameson Bridgwater has been appointed to conduct the examination to determine whether the charging schedule is sound.

Programme Officer

An independent Programme Officer, Liz Sheard, has been appointed to assist the independent Inspector through the examination. She is responsible for all procedural matters of the examination and all future correspondence with respondents to the CIL regarding the examination will be via her.

Contact Details

Liz Sheard
[email protected]
01423 556952
Programme Officer, c/o Harrogate Borough Council, PO Box 787, Harrogate, HG1 9RW


Draft Charging Schedule submission for examination

The Community Infrastructure Levy Draft Charging Schedule was submitted for examination on Friday 16 August 2019.

Full details are contained within the Notice of Submission Statement.

Draft Charging Schedule Submission documents

The Submission Draft Charging Schedule and supporting documents are available to view below:

Submission Draft Charging Schedule August 2019
Draft Charging Schedule January 2019
CIL Viability Assessment January 2019
Regulation 19b Consultation Statement and Key Issues: August 2019
Consultation responses

Supporting documents relevant to the preparation of the Draft Charging Schedule:
Whole Plan Viability Study, October 2016
Infrastructure Delivery Plan, August 2018
Preliminary Draft Charging Schedule May 2018
Preliminary Draft Charging Schedule Key Issues January 2019
Planning Obligations Evidence Tables May 2018

All representations submitted during the publication consultation have been submitted to the Planning Inspectorate (including any attachments and supplementary reports). These are available to view on the consultation portal or from the list above.

Hard copies of the submission documents will also be available for inspection at the following locations:


The Community Infrastructure Levy (CIL) allows councils to raise funds from developers undertaking new building projects in the district. The money can be used to fund infrastructure projects such as schools, open space, flood defences and transport improvements that are needed to support development.

Charging authorities set out the CIL rates in a charging schedule. CIL rates are expressed in pounds per square metre and will be levied against most new development. The council must set CIL rates based on evidence of the viability of different types of development and produce a charging schedule that is subject to an independent examination.

Preparation of a charging schedule is undertaken in three stages:

  1. Preparation and consultation on a Preliminary Draft Charging Schedule (PDCS)
  2. Revision of the PDCS and consultation on a Draft Charging Schedule and
  3. Examination in public of the Draft Charging Schedule and receipt of a binding inspector's report

Preliminary Draft Charging Schedule consultation.

A six week consultation on the Preliminary Draft Charging Schedule (PDCS) ran from 26 May to 6 July 2018. The consultation documents can be viewed from the links below

Preliminary Draft Charging Schedule 2018
Planning Obligations Evidence Tables 2018
Zone 2 Ripon map

Page last updated 04/08/2020