Due to be completed in November 2021, the multi-million-pound investment project at Ripon Leisure Centre will provide a new state-of-the-art facility with:
- a six-lane 25 metre pool
- a new main entrance, lobby and changing rooms
- a new health suite
- two new dance studios and spin studio
- new £100,000 play area
Key project updates:
- the gym has temporarily moved to the arts hall and is now available for existing members
- the plant room is currently being installed in preparation for the new swimming pool as well further improves on the interior, including electric and flooring
- work continues outside including grout testing, installation of drainage and levelling of the field to allow for the football pitch and car park
- created a temporary car park, footpath and entrance at the rear of the building, accessed from Knaresborough Road